Professional cable manufacturer
Both methods run cables underground. But the difference in ampacity, installation speed, and 25-year maintenance cost is bigger than most project teams realise.
★ TCO Analysis — Solar Farm CablingI’ve worked on enough solar projects to know that the choice between direct burial and duct (conduit) is rarely a straightforward one. On paper, both methods put the cable in the ground. But once you factor in thermal derating, installation speed, and what happens when something goes wrong 12 years in, the two paths diverge dramatically.
Here’s the headline: direct burial typically costs less upfront and delivers better ampacity, while duct installation costs more but makes future cable replacement far easier. Which one wins on total cost of ownership depends on your soil, your layout, and how much cable replacement risk you’re willing to carry.
Let me break it down with the numbers I’ve seen in real projects.
They both go in a trench, but the engineering requirements are not the same.
Direct burial means the cable is in direct contact with the soil. There’s no secondary mechanical barrier. So the cable itself must provide everything:
In a duct installation, the conduit takes the mechanical load. The cable can be a standard construction (though it still needs to handle pulling tensions):
This is where the two methods really separate. Direct burial is faster and cheaper to install. But the gap narrows when you look at the whole lifecycle.
| Step | Direct Burial | Duct Installation |
|---|---|---|
| Trench excavation | Same for both | Same for both |
| Sand bedding | Lay 100 mm sand | Lay 100 mm sand + concrete encasement (if required) |
| Cable/conduit placement | Lay cable directly | Assemble and lay conduit; wait for joint glue to cure |
| Pull boxes | None needed | Install at intervals (±100–150 m) |
| Cable pulling | Not required (cable laid in trench) | Pull cable through conduit — requires pull line, lubricant, tension monitoring |
| Cover/protection | 100 mm sand + protection slab + warning tape | Backfill around conduit |
| Backfill | Same for both | Same for both |
| Testing | IR test after backfill | IR test after pulling (before backfill) + after backfill |
| Estimated crew-hours per km | ~200–300 | ~350–500 |
| Item | Direct Burial (per km) | Duct Installation (per km) |
|---|---|---|
| Trenching (0.6 m × 0.8 m, soft soil) | $13,000–$39,000 | $13,000–$39,000 |
| Sand bedding material | $1,500–$3,000 | $1,500–$3,000 |
| PVC conduit (2 × 4" schedule 40) | — | $10,000–$20,000 |
| Concrete encasement (if required) | — | $8,000–$25,000 |
| Pull boxes / handholes | — | $3,000–$8,000 |
| Protection slab + warning tape | $2,000–$4,000 | — |
| Cable laying labour | $8,000–$15,000 | $15,000–$30,000 |
| Cable pulling equipment | — | $2,000–$5,000 |
| Total estimated (per km) | $24,500–$61,000 | $52,500–$130,000 |
| Cable material cost | ~30% more copper (vs free-air, see Section 3) | ~40% more copper (vs free-air; more derating than direct burial, requiring larger cross-section) |
| Costs are indicative ranges for US market in soft soil. Rock removal adds 20–50% to excavation. Chinese market prices are approximately 40–60% lower for labour-driven costs. Cable material costs vary with copper prices. | ||
The two biggest long-cost items that don’t show up in the installation budget: thermal derating (which affects cable sizing) and fault repair cost (which affects O&M).
Here’s the physics: both methods embed the cable in soil, which is a poor thermal conductor. But conduit adds another layer of thermal resistance — the air gap inside the conduit and the PVC or HDPE wall itself.
A detailed IEEE study comparing the two methods found that for a typical MV cable at a soil thermal resistivity of 1.2 °C·m/W:
| Parameter | Direct Buried | In Conduit | Difference |
|---|---|---|---|
| Ampacity (single circuit, trefoil, at rho 1.2 °C·m/W) | ~204 A | ~155 A | −24% in conduit |
| Thermal bottleneck | Soil dry-out around cable | Trapped heat inside duct + soil | — |
| Impact of soil resistivity increase | Significant (−50% possible) | Even more significant | — |
| Multiple circuits (4 trefoil, touching) | ∼70% of single circuit | ∼60–65% of single circuit | Conduit derates more |
The IEEE paper concluded: “For the range of soil thermal resistivities found in North America, the cable buried in conduit has an ampacity lower than a direct buried cable at all locations.”
But here’s what that means in practical terms. If your design load is 180 A per circuit and you’re choosing between burial methods:
| Scenario | Direct Burial | Duct Installation |
|---|---|---|
| Cable fault repair | Dig to locate, excavate to access, splice cable, re-bury. 2–5 days per fault. Cost: €12,000–€17,000 per splice (industry estimate, European O&M data). | Identify section, pull out damaged cable section, pull in new cable via existing duct. 1–2 days. Cost: €5,000–€10,000. |
| Conduit/cable damage from external excavation | High risk — no physical barrier protecting the cable | Lower risk — conduit provides mechanical protection, but if struck, both conduit and cable may need repair |
| Water ingress | Low risk — cable in direct contact with soil; moisture is distributed | High risk if duct not sealed — water accumulates in conduit, submerged cable may fail prematurely |
| Rodent damage | Risk depends on armouring and local rodent activity | Lower risk — conduit adds a barrier |
| Cable replacement (full string) | Requires full re-trenching — disruptive and expensive | Old cable pulled out, new cable pulled in — no excavation needed if duct is intact |
Here’s the honest engineering trade-off: in 15 years of solar farm O&M, I’ve seen roughly one cable fault per 50–100 km of buried cable per year, on average. Most are caused by third-party excavation, not insulation failure. The question is whether you’re willing to bet the long-term O&M budget on a low fault probability (direct burial saves installation cost) or whether you want to make every eventual repair cheaper (conduit costs more now, less later).
| Cost Item | Direct Burial | Duct Installation |
|---|---|---|
| Initial installation cost | $30,000–$70,000 | $60,000–$150,000 |
| Cable material (MV, 3-core 95–240 mm²) | $50,000–$120,000 | $60,000–$150,000 (typically 1–2 sizes larger) |
| Expected cable faults (25 yr, ~0.3 faults/km) | $15,000–$25,000 (3 repairs × $5k–$8k each) | $6,000–$12,000 (3 repairs × $2k–$4k each) |
| Water ingress remediation | — | $5,000–$15,000 (duct pumping/sealing if needed) |
| Total 25-year TCO (per km) | $95,000–$215,000 | $131,000–$327,000 |
| TCO projection assumes soft soil, moderate fault probability. Rock, aggressive soil, or high third-party excavation risk shifts the balance toward conduit. Brownfields or sites with expected future modifications strongly favour duct. | ||
On straight TCO, direct burial wins in most stable-soil scenarios by roughly 25–35%. But that gap narrows significantly — and sometimes inverts — in challenging ground conditions or when future cable replacement is likely.
Not every cable is built for underground service. Here’s how Sorivo’s product range maps to each installation method.
| Application | Installation Method | Recommended SORIVO Cable | Key Feature for Underground Service |
|---|---|---|---|
| PV DC strings | Direct burial (in conduit) | H1Z2Z2-K 4–25 mm² | EN 50618, tinned copper, 1500 V DC, UV + moisture resistant sheath |
| PV DC strings | Direct burial (no conduit) | H1Z2Z2-K in sand/concrete-encased trench + warning tape | Additional protection layer recommended; cable designed for outdoor exposure, not direct earth contact |
| AC collection (LV, 0.6/1 kV) | Direct burial | CU/XLPE/SWA/PVC | Steel wire armour for mechanical protection, PVC sheath for moisture resistance, BS 5467 / IEC 60502-1 |
| AC collection (LV, 0.6/1 kV) | In duct | CU/XLPE/SWA/PVC or CU/XLPE/LSZH/SWA/LSZH | SWA still recommended for pulling protection; LSZH variant preferred if ducts are in confined spaces |
| MV collection (11–33 kV) | Direct burial or duct | MV XLPE armoured cable (contact Sorivo) | TR-XLPE insulation, water-blocking, metallic screen for earth fault detection |
| BESS DC connection | Direct burial or duct | TÜV 2PfG 2642 ESS cable | Chemical-resistant sheath, 1500 V DC, TÜV certified for BESS environments |
The difference between a premium solar cable and a generic economy cable shows up most clearly in underground installations — where moisture, soil chemistry, and thermal cycling are relentless over 25 years.
| Feature | Market Generic / Economy | SORIVO Premium Grade |
|---|---|---|
| Conductor | Bare copper — tarnishes in buried environments, increases contact resistance | Tinned copper per IEC 60228 Class 5/6 — corrosion-resistant, stable contact resistance over 25 years |
| Insulation | Variable XLPE cross-linking — may degrade faster in wet underground conditions | Verified cross-linking per EN 50618 / IEC 62930 — full 90 °C rating, tested wet insulation resistance |
| Moisture resistance | Standard jacket — water ingress likely over time in direct burial | Water-blocking options available — meets wet withstand test per IEC 60502-1 |
| Armour (where applicable) | Under-gauge galvanised wire — corrodes faster in buried environments | Full-gauge galvanised SWA per BS 7655 — proven corrosion resistance for underground service |
| Traceability | None — impossible to verify conductor size after burial | Metre-marked sheath, batch traceable — full material certification available before burial |
| Factory testing | Batch sample only | 100% factory tested: conductor resistance, IR, high-voltage withstand, spark test |
| Certification | Self-declared CE — no third-party verification for underground performance | TÜV / UL / BASEC certified — independently verified for direct burial and duct installation |
Need cable specifications for your solar farm installation?
Sorivo provides factory test data, ampacity calculations for direct burial and duct conditions, and full material certifications with every order. Contact our engineering team for project-specific cable sizing.
sale@sorivocable.com | +86 19282905529
LV Armoured Power Cables → H1Z2Z2-K Solar Cables → Renewable Energy Solutions →
