Professional cable manufacturer
CABLE INSTALLATION ENGINEERING · 2026-09-12
Two numbers decide whether a pull is safe: the tensile force in the conductor and the sidewall pressure at every bend. This page gives the formulas, the friction values worth trusting and the ones that are guesswork, a worked 95 mm² SWA example you can recompute — and an honest account of which documents actually set these limits, because one of them does not.
Cable installed badly and cable installed well look identical from the outside. The damage happens during the pull and shows up years later as a jacket split, a deformed core or a failure at a bend. The calculation is not difficult; what makes it unreliable in practice is that different documents give different limits, and the two most commonly cited authorities are cited for the wrong thing.
Limit 1 — tensile force in the conductor. Worked out along the route: friction accumulates on straight runs, and tension multiplies around bends by the capstan factor eμθ.
Limit 2 — sidewall pressure at each bend. The tension leaving the bend divided by the bend radius. It is a separate check, and on long pulls with tight bends it is frequently the one that fails first — even when the winch gauge looks comfortable.
Both must be checked against cable-specific limits. Those limits come from the cable datasheet and from the installation guides listed in section 02 — not from IEC 60502.
The reason sidewall pressure catches people out is that it scales with tension but inversely with radius. A pull that sits comfortably inside the conductor limit at 40 % can exceed the sidewall limit at a single tight bend, because the tension has already multiplied around the earlier route. The worked example in section 07 demonstrates exactly that, with the same cable and the same tension in both cases.
This section exists because the most common error in cable pulling calculations is sourcing the limits to the wrong standard. We have made this error on this page in a previous version, so it is worth being explicit about what each document does and does not contain.
| Document | What it actually contains | Does it set a pulling limit? |
|---|---|---|
| IEC 60502-1 | Construction, dimensions and test requirements for extruded-insulation power cables up to 1 kV. Current edition carries a special bending test as clause 18.17. | No. No pulling tension limit and no numeric bending radius appear anywhere in it. |
| IEC 60364-5-52 | Wiring installation requirements, including a clause stating that the bend radius shall be such that cables are not damaged. | No numeric value. It states the performance requirement, not the figure. |
| IEEE Std 1185 | Guide for installation of cable systems, including pulling tension and sidewall pressure calculation methods. | Yes — calculation methods and the conductor stress constant commonly used. |
| IEEE Std 576 | Recommended practice for installation, termination and testing of insulated conductors, with the straight and sloped pull equations. | Yes — calculation methods. |
| AEIC CG5 | Underground extruded power cable pulling guide, including sidewall pressure and grip tables. | Yes — pulling practice, including grip limits. |
| CIGRE Technical Brochure 889 | Installation of high-voltage cable systems, including pulling force calculation for complex routes and multiple cables per duct. | Yes — methods, particularly for HV and long sections. |
| Manufacturer datasheet and installation manual | The construction-specific figures: minimum bend radius, mass per metre, outer diameter and, where published, a pulling limit. | Yes — and this is the figure that governs. |
| ANSI/ICEA P-45-482 | Short-circuit performance of metallic shields and sheaths on insulated cable. | No. It is not a pulling guide, despite frequent citation as one. |
Scope statements taken from the IEC webstore entries for IEC 60502-1 and IEC 60364-5-52, the IEC 60502-1:2004 table of contents, IEEE 1185-2019 and IEEE 576-2000, the AEIC CG5 reference in trade technical guidance, and the publisher preview of ANSI/ICEA P-45-482-2017.
Break the route into segments and carry three quantities: the tension entering the segment, the geometry of the segment, and the tension leaving it. Work from the cable end back towards the winch, or from the winch forward — the arithmetic is the same, but for short pulls the bend factor is applied to the tension already in the cable, which is what makes bends disproportionately expensive.
For a horizontal straight run, tension accumulates as friction against the cable's own weight:
T = μ · W · L
For a sloped run the weight component along the route is added or subtracted depending on direction, giving the two forms used in IEEE 576 and IEEE 1185:
slope up: T = L · W · (μ cos θ + sin θ) slope down: T = L · W · (μ cos θ − sin θ)
Where W is the cable weight per unit length in newtons per metre, L is the segment length in metres and μ is the friction coefficient.
Tout = Tin · eμθ
θ is the angle of wrap in radians. This is the one conversion worth double-checking: IEEE 1185's annex presents the slope angle in degrees, while European manufacturers and most installation software work in radians, and a factor of 57 between the two produces a spectacularly wrong answer. One caution on our own part: we present θ in radians here because that is the convention in the capstan relation as used in the manufacturer installation guides; if your calculation sheet uses degrees anywhere, convert before you compute.
For calibration, the multiplier is 1.48 at 45° and 2.19 at 90° for a friction coefficient of 0.5, and works out at about 1.60 for a 90° bend at μ = 0.30. Three 90° bends in series do not add — they multiply, and that is why route design matters more than winch capacity.
| Condition | μ | Basis |
|---|---|---|
| Measured, lubricated PVC jacket in PVC conduit | 0.11 | Measured by friction-table method |
| Measured, lubricated XLPE jacket | 0.06 – 0.11 | Measured by friction-table method |
| Rollers and well-maintained sheaves | approx. 0.15 | Manufacturer guidance |
| Lubricated duct, PE jacket against PE duct | 0.25 | Manufacturer design table (assumed) |
| Lubricated duct, PVC jacket in PVC duct | 0.30 – 0.50 | Manufacturer design table (assumed) |
| Three cables in one duct, lubricated | 0.45 – 0.85 | Manufacturer design table (assumed) |
| Dry duct or conduit | above 1.0 possible | Industry technical guidance |
| Default when the condition is unknown | 0.5 | Common industry default |
| Direct burial | not published | We did not find a credible measured figure |
| LSZH jacket, lubricated | not published | We did not find a measured value; some LSZH compounds require specific lubricants |
Measured values from lubricant manufacturer friction-table test data for PVC conduit. Assumed values from a major European cable maker's installation friction table. Note the scale of the gap: measured lubricated values sit at 0.11 or below, while design tables commonly assume 0.25–0.50. Using a design-table value is conservative. Using 0.5 as a default when a lubricated pull is planned may overstate tension by a factor of four or more — which is wasteful but safe, and far better than the reverse. We found no published friction coefficient for direct burial or for LSZH sheaths, and we are not going to invent one.
Sidewall pressure is the force the cable applies to the outside of the bend, per unit length of cable in contact with it:
P = T / R
T is the tension in newtons and R the bend radius in metres, giving P in newtons per metre. Some references use the tension entering the bend and some the tension leaving it; we use the exiting tension, which is the higher of the two and therefore conservative. In imperial units the same relation gives pounds-force per foot.
| Limit | lbf/ft | kN/m | Where it comes from |
|---|---|---|---|
| General default | 300 | 4.38 | Widely applied general limit in North American technical guidance |
| Higher limits published for larger conductors | above 300 | above 4.38 | Individual manufacturer datasheets; the value is construction-specific |
Conversion used: 1 lbf/ft = 0.014594 kN/m. We have deliberately not filled this table with manufacturer-specific numbers beyond the general default, because the permissible sidewall pressure is a property of the specific cable: jacketed, lead-sheathed and interlocked-armour constructions differ, and the figures we could find for individual constructions could not all be re-verified against a live published source at the time of writing. The 300 lbf/ft figure is the most widely applied general default and is what we would use when a datasheet is silent — but where a datasheet or an installation specification gives a different figure, that figure governs.
The radius that matters during installation is not the radius the cable will have in service. Cable bent to its minimum installed radius and then pulled around that curve experiences a sidewall pressure that the same bend in its final position never sees. Manufacturer practice is therefore to double the requirement during laying: an SWA multicore cable with a minimum installed radius of eight times the outer diameter is commonly pulled at sixteen times.
Because the standard route gives no figure — IEC 60502-1 contains none, and IEC 60364-5-52 states only that cables shall not be damaged — the numbers you work from are the manufacturer's published minimums plus the project's own laying specification. For a route being designed, the design decision is the opposite of the calculation: choose radii large enough that the sidewall check passes at the tightest bend with margin, rather than discovering the failure at the winch.
Fill matters for the same reason. Several cables in one duct share the space, bear on each other, and produce a combined sidewall load on the duct wall that is higher than any single cable would generate. Design tables for lubricated multiple-cable pulls start at μ = 0.45 with three cables in a duct, against 0.25–0.30 for a single cable — a 50 % to 80 % increase in the friction term before any bend is encountered. If the duct is already installed and congested, that number should be used even if the pull is well lubricated.
The maximum tension a pull may develop is not one number but two, and they rarely coincide: what the conductor can bear, and what the pulling attachment can transmit into the cable.
| Conductor | Imperial rule | Metric equivalent |
|---|---|---|
| Copper | 0.008 lbf per circular mil | approx. 70.2 N/mm² |
| Aluminium, 3/4 hard and AA-8000 | 0.006 lbf per circular mil | approx. 52.7 N/mm² |
| Copper, European manufacturer practice | — | 50 N/mm² |
| Aluminium, European manufacturer practice | — | 30 N/mm² |
The imperial rule comes from an ICEA-sponsored study and is reproduced in distributor technical guidance; it is a manufacturer and industry rule of thumb rather than a mandatory standard clause. The metric equivalents shown are the ones European manufacturers publish, and we are conscious that they do not agree with the imperial rule — 50 N/mm² against roughly 70 N/mm² for copper is a 30 % difference in the permissible load. We are showing both rather than selecting one. For aluminium the rule depends on temper: one distributor's tabulation puts hard-drawn aluminium at the same 0.008 figure as copper, while soft solid aluminium can be considerably lower.
The consequence is that a calculation showing 5 kN of required tension can be perfectly acceptable against a 6.7 kN conductor allowance and still exceed the grip limit if the pull is being made on a stocking grip rather than a pulling eye. The attachment is part of the calculation, not an afterthought — and where armour, grip and conductor give three different numbers, the lowest of the three governs.
The route below is deliberately ordinary: a ducted pull with one 90° bend. All inputs are stated so the arithmetic can be recomputed.
| Input | Value | Source or assumption |
|---|---|---|
| Cable | 4 × 95 mm² Cu, XLPE insulated, SWA armoured, LSZH sheathed, 0.6/1 kV | Construction under test |
| Outer diameter | 42.3 mm | Manufacturer datasheet for this construction |
| Mass | 5.60 kg/m | Heaviest of three published figures checked; we take the heaviest deliberately |
| Weight per unit length, W | 54.9 N/m | 5.60 × 9.81 |
| First straight section | 120 m | Route |
| Bend | 90°, radius 1.2 m | Route; 1.2 m is about 28 × OD |
| Second straight section | 40 m | Route |
| Friction coefficient, μ | 0.30 | Assumed, lubricated single cable in duct |
| Conductor allowance, copper | 70.2 N/mm² | Imperial rule of thumb |
Outer diameter and mass checked against three published datasheets for 4 × 95 mm² constructions: 42.3 mm and 5,245 kg/km for a flexible Class 5 build, and 41.3 mm / 41.7 mm at approximately 5,280 and 5,600 kg/km for hard Class 2 builds. We use 5.60 kg/m, the heaviest, because a heavier cable produces higher tension and we would rather overstate the requirement than understate it.
T1 = 0.30 × 54.9 × 120 = 1,976 N
90° is 1.5708 radians, so μθ = 0.4712 and the capstan multiplier is e0.4712 = 1.60.
T2 = 1,976 × 1.60 = 3,162 N
T3 = 3,162 + (0.30 × 54.9 × 40) = 3,162 + 659 = 3,821 N
Allowance = 95 mm² × 70.2 N/mm² = 6,669 N
The required pull tension is 3,821 N, which is 57 % of the imperial rule of thumb. Against the European manufacturer figure of 50 N/mm² the allowance is 4,750 N, so the same pull uses 80 % of it. Both are inside their limits — but note that the answer to "is this pull acceptable?" changes materially depending on which rule the specification follows, which is exactly why the rule should be fixed in the method statement before the pull, not chosen afterwards.
P = T2 / R = 3,162 / 1.2 = 2,635 N/m = 181 lbf/ft
At 181 lbf/ft this is roughly 60 % of the 300 lbf/ft general default — the figure we would use when a cable datasheet is silent. On that basis the bend passes with margin; if the datasheet for the cable in hand publishes a higher permissible value, the margin is greater still.
Calculation gets you a route and a limit. These are the checks that decide whether the pull on the day matches the calculation.
Two of those items are the subject of their own pages. Equipment selection and the pre-installation checklist are set out in the contractor's pre-installation checklist and tension guide, and the hardware for long pulls — winches, tension monitors, rollers and grips — is covered in cable pulling tools for large installations. This page deliberately stays on the calculation; general laying methods and requirements sit in our guide to cable laying methods.
We publish construction data. For our CU/XLPE/LSZH/SWA/LSZH 0.6/1 kV armoured cable, that means IEC 60502-1 and BS 5467 construction, a minimum bend radius of twelve times the outer diameter for multicore and fifteen times for single-core, and, on request, the outer diameter and mass per metre for a specific size — which is what you actually need for the arithmetic above. If you are running a pull calculation, ask for those two figures for the exact construction and size quoted, not for a generic table, because the difference between a Class 2 and a Class 5 build of the same nominal size is material to the answer.
What we will not do is quote a pulling limit we cannot substantiate. We do not publish a blanket maximum pulling tension for a construction family, because the limit belongs to the conductor build and the attachment, and it changes with the size. We could not locate any IEC, EN or BS test for pulling-induced damage — IEC 60502-1's test list contains a bending test but no pulling test, and the tensile test that exists in IEC 60794 applies to optical fibre cable, not power cable. So there is no certification that says a cable survives a pull; there is only the calculation, the route, and the discipline of stopping when the number is reached. We would rather say that plainly than imply a guarantee the standards do not offer.
Tell us the cable construction and size, the segment lengths and bend radii, the duct or tray details and the intended lubrication. We will return the outer diameter and mass per metre for the exact construction, the bend radius we publish for it, and our reading of which limit governs your route.

No. IEC 60502-1 sets construction, dimensions and test requirements for extruded-insulation power cables; neither its 2004 nor its 2021 edition contains a pulling-tension clause or a numeric bend radius. Pulling limits come from the cable manufacturer's datasheet and from the installation guides — IEEE Std 1185, IEEE Std 576 and AEIC CG5-2015.
For copper conductors the widely published rule of thumb is 0.008 lbf per circular mil, approximately 70 N/mm², with aluminium at 0.006 lbf per circular mil. European manufacturers often publish lower allowances of 50 N/mm² for copper and 30 N/mm² for aluminium. The governing figure is the one on the cable datasheet, and the pulling attachment may impose a lower limit again.
Multiply the tension entering the bend by the capstan factor e raised to the power of the friction coefficient times the angle of wrap in radians. For a 90° bend at a friction coefficient of 0.30, the multiplier is about 1.60; at 0.50 it is about 2.19. Multiple bends multiply rather than add, which is why route design dominates the calculation.
Sidewall pressure is the tension at the exit of a bend divided by the bend radius, expressed in newtons per metre or pounds-force per foot. Published limits differ. 300 lbf/ft is the widely used general default in North American technical guidance, and individual manufacturers publish higher figures for particular constructions. The correct limit is a property of the cable and should come from its datasheet.
Measured values for lubricated cable runs are low: around 0.11 for a lubricated PVC jacket in PVC conduit and 0.06 to 0.11 for XLPE. Design tables commonly assume 0.25 to 0.50, and 0.5 is the usual default when conditions are unknown. Assumed values are conservative; the risk lies in assuming a low figure for a dry or congested duct.
Usually sidewall pressure at the tightest bend. In a worked example with the same cable and identical tension, a bend at 1.2 m radius sits at 181 lbf/ft and passes comfortably, while the same bend at 0.68 m radius reaches 319 lbf/ft and exceeds the 300 lbf/ft general default — even though the conductor is only at 57 % of its allowance.